Investigation of fires and arc flash events in which electrical equipment is alleged to be the cause. The investigation follows the scientific method set out in NFPA 921 and tests each hypothesis against the evidence.
Fire damages wiring. Arcing found at a fire scene may be what started the fire, or it may be what the fire did to energized conductors on its way through. Telling the two apart, through arc mapping, the sequence in which circuits failed, and the state of every overcurrent device, is the central electrical question in most fire matters. PEFG typically works alongside the origin-and-cause investigator, answering the electrical questions the fire investigation raises.
NFPA 921 calls for the scientific method, and courts frequently look to NFPA 921 when a fire opinion is challenged:
Opinions are stated to a level of certainty. A probable cause is more likely than not; a possible cause is not. When two or more hypotheses cannot be eliminated with the evidence available, undetermined is a valid conclusion, and a more defensible one than a forced choice.
The investigation file should show, step by step, that each was avoided.
When an arc flash injures a worker, two questions usually run in parallel: why the equipment failed or the arc was initiated, and whether the incident energy, arc flash boundary, labeling, and PPE were what IEEE 1584 and NFPA 70E required. The second question needs the system configuration as it was at the moment of the incident, not as it appears in the current study. See arc flash analysis.
After six years in service, a medium-voltage air-insulated switchgear lineup failed at the end of an A-phase voltage-transformer bushing, and video captured the arc flash. The recording shows the fault progressing from A-phase-to-ground, to A-B phase-to-phase, to a three-phase fault that continued until cleared.
The bushing was cast cycloaliphatic epoxy with an inner high-voltage screen and an outer grounded screen. On the failed part the two screens were not concentric: the smallest spacing between them sat near the failure location, and a void was observed in the casting.
The manufacturer’s stated dielectric strength of 330 V per mil sets the margin. The roughly 15.6 kV phase-to-ground stress of a 27 kV solidly grounded system needs only about 47 mil of epoxy, but withstanding the 125 kV impulse level of that voltage class takes about 379 mil, close to 3/8 in., which is the design spacing. A rough measurement of the thinnest section came out just under 10 mm, at the minimum for the impulse level, before accounting for the off-center screens and the void.
The root cause was a poorly manufactured bushing with voids in the insulating material. A subsequent audit at the manufacturer found that production staff had not followed the manufacturing instructions and had deviated from the specified steps. Those deviations, together with poor control of the vacuum process meant to extract air pockets and of the concentric spacers that position the internal screens, produced the voids and the off-center screens that led to the failure. As of the 2024 presentation, corrective actions were in place and no further failures had been reported.
Download the printable checklist and evidence log (PDF, 2 pages) →
It can help. Arc mapping records where arcing occurred on each circuit; because an energized circuit usually arcs first where the fire first reaches it, the pattern across several circuits can point back toward the area of origin. It is one line of evidence among several, and it has to be consistent with the fire patterns, the witness accounts, and the recorded data.
Then the report should say so. Under NFPA 921, when two or more hypotheses cannot be ruled out with the available evidence, the cause is undetermined. An opinion that names a probable cause the evidence does not support is exactly what a reliability challenge is designed to exclude.
No. On most fire matters PEFG works alongside the origin-and-cause investigator, answering the electrical questions: whether a circuit or device was capable of ignition, whether the arcing is cause or effect, and what the protective devices and recorded data show.
Direct principal access. Conflict check and retention letter typically within one to two business days.